It seems to be a discrepancy between the information that we have received during the consultation period and the information that we have received via the Freedom Of Information Act.
The following clarifications have been received by the council. See the original letter here
It seems to be a discrepancy between the information that we have received during the consultation period and the information that we have received via the Freedom Of Information Act.
We have requested some clarifications from the council but Mr Mike Fegredo, Contract Manager for those works, has described our requests for information as a "futility of such petty endeavours."
Today, Apollo workers removed the parts of the old boilers and equipment that was inside the boiler room. As you can see from the picture all the metals are rusty and beyond repair.
However, those are the boilers that Camden Council employees have told us during the last major works that were fit for another 10 YEARS.
The following letter was sent to the residents of the Curnock Estate concerning the hot water. Unofrtunately the hot water is still a problem on the 05th June 2013. The original document can be found on this link.